Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.


Appendix H: Audit Program for the Post-Installation Stage

Stage: 7. Post-installation Stage

Objective: 7.A To establish that the system operates in accordance with the design objectives and other measurement criteria, and project costs/benifits have been achieved.

Criterion: 7.A.1 A formal post-installation review has been undertaken and the results reported to management.

Audit Step: 7.A.1.1 Has a Post-Installation report or similar document been prepared?

Y N N/A Comments XREF
         

Audit Step: 7.A.1.2 Verify that it contains the following:

  • documentation of the system's actual achievements
  • comparison of those achievements against the original objectives
  • recommendations for improvements
  • actual resource use, compared to the original plan, with reasons for variance
  • actual milestones achieved, compared to the original plan, with reasons for variance
  • updated cost/benefit analysis
Y N N/A Comments XREF
         

Audit Step: 7.A.1.3 Verify actual resource use in source documents.

Y N N/A Comments XREF
         

Audit Step: 7.A.1.4 Verify the updated cost/benefit analysis against source documents.

Y N N/A Comments XREF
         

Audit Step: 7.A.1.5 Determine that the updated cost/benefit analysis has taken into consideration the human resource impact requirements.

Y N N/A Comments XREF