ARCHIVED - Project Planning Process


Warning This page has been archived.

Archived Content

Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.

2. Process

2.1 Entry Criteria

The following entry criteria describes the input's state, an event, or an expired amount of time, which is required before this process can begin.

Details of Entry Criteria
  • Approved Business Case
  • Approved Project Charter
  • Approved Set of Requirements, as required by your IM/IT methodologies

2.2 Process Map

The overall process flow given below shows the interaction and flow among the activities. More details about the activities can be found in 2.4 Activities.

Process Map (4969 bytes)

2.3 Inputs

The following inputs are used in this process. Where they don't exist, identify any associated risks.

Input Detail of Inputs and remarks Ref.
Business Case The identification and justification of an IM/IT project that relates the IM/IT project to program priorities and the measurable improvements in program performance.
  • Identifies the opportunity
  • Describes the added value
  • Describes the IM/IT solution
  • Identifies the indicators to measure improvements in program performance
EMF Business Case Guideline
Project Charter An agreement between technical and business groups defining:
  • Partners & external stakeholders
  • Project management framework
  • Roles, responsibilities, accountabilities and activities
  • Management commitments
  • Empowerment framework
EMF Project Charter Template
Enterprise Database
  • Actuals from previous IM/IT Projects for comparison and verification of the planning process.
 
IM/IT Methodology Deliverables
  • Architectures, processes, templates, etc…
 

2.4 Activities

The following activities are performed in this process. Document all assumptions, risks, constraints etc. in the Project Plan.

No. Activities Action by Detail of Activities and Remarks Ref.
1 Requirements Management PM
  • Requirements management in the context of overall project management is documented in PPTO-PS-001 Project Management Process.
PPTO-PS-001
2 Negotiate Commitment PM
  • Negotiations have begun.
  • Estimates (activities 3-6) must be done in parallel with other planning activities before final commitment.
 
3 Decompose Requirements PM
  • Create a Work Breakdown Structure (WBS). Identify the processes and deliverables for the project and map the requirements to processes and deliverables. The WBS should reflect organisational System Development Life Cycle (SDLC).
  • Review WBS with affected groups and individuals.
  • If requirements are divided into interdependent individual projects a multi project plan will be required to cover interdependencies and integration.
PPTO-TM-002
4 Estimate Product Size PM
PTM
  • Estimate Product Size for each product element using your organisation's estimation methods, tools and techniques. In the absence of the above use the referenced procedure for estimating software product size.
  • Project tracking in the context of overall project management is documented in the referenced documents.
PPTO-PD-001

PPTO-TM-002

5 Estimate Project Resources PM

PTM

  • Estimate Project Resources using your organisation's estimation methods, tools and techniques. In the absence of the above use the referenced procedure for estimating project resources.
PPTO-PD-002

PPTO-TM-002

6 Develop Schedule PM

PTM

  • Develop Schedule using your organisation's estimation tools and techniques. In the absence of the above use the referenced procedure for developing schedule.
  • Does Plan meet need?
    [YES] results in obtaining approval of the project plan. Go to activity 7.
    [NO] results in re-negotiating requirements (i.e. De-Scope or more effort, schedule, or funds). Then re-plan. Go to activity 2.
PPTO-PD-002

PPTO-TM-002

7 Obtain Commitment and Approval PL

PM
PTM

  • Approval is received from all affected groups and individuals.
 
8 Project Tracking ALL
  • Project tracking in the context of overall project management is documented in the referenced documents.
PPTO-PS-001
PPTO-PS-003

2.5 Outputs

The following outputs are produced or modified by the activities in this process.

Output Detail of Outputs and Remarks Ref.
Project Charter
  • Possible modifications
EMF Project Charter Template
Project Plan
  • Project estimates are included in the Project Plan
PPTO-TM-002
Project Deliverables
  • Deliverables the customer will receive
 
IM/IT Methodology Deliverables
  • Deliverables the IM/IT organisation requires to produce the solution
 
Enterprise Database
  • Compare original estimates to actuals
  • Update historical data for use in future projects
 

2.6 Verification and Validation

Output Validation To determine if the outputs are within specification,
  • Use the (PEER-PS-001) Peer Review Process and any techniques described in your IM/IT methodology.
  • Use validation techniques referred to in your IM/IT methodology such as testing, demonstration, analysis and inspection.
 

2.7 Exit Criteria

Details of Exit Criteria
  • Approved Project Plan.

2.8 Metrics

Refer to Enhanced Management Framework, Exposure Draft Executive Toolkit, November 22, 1999 for the Project Health Check Dashboard.

2.9 Records Control Table

Not applicable at this time. Populate table if seeking ISO certification. For more information, refer to (PPTO-TM-001) Process/Procedure Template.

Description
(no. and name)
Storage Location Filing / Index Minimum Storage Period
       
       

2.10 Controlled Documents Table

Not applicable at this time. Populate if seeking ISO certification. For more information, refer to (PPTO-TM-001) Process/Procedure Template.

Number Name Revision Date
(or version)
Owner