Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.

3.2.3 Status Report on Projects operating with specific Treasury Board Approval2


($ Millions)
Project Original Estimated Total Cost Revised Estimated Total Cost Actual Total Cost 2009-2010
Main
Estimates
Planned
Spending
Total Authorities Actual Expected date of close-out
Laboratory Renovation and Consolidation in Burnaby, BC 6.9 6.9 5.6 4.5 4.5 4.5 4.4 2009-10
Skyline Complex 9.6 9.6 8.3 0.1 0.7 0.8 0.8 2010-11
Canada's Economic Action Plan 24.0 24.0 8.0 0 0 9.8 8.0 2010-11
Food Safety Action Plan 32.7 32.7 7.7 8.6 8.6 9.9 5.4 2012-13

2Figures are inclusive of Employee Benefit Plans (EBP)

3Very first Treasury Board Expenditure Authority decision for total project cost.

4Most recent Treasury Board Expenditure Authority decision for total project cost.

5Include the current year.