Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.

Section III: Supplementary Information

3.1 Link to the Government of Canada Outcomes Areas

The whole-of-government framework for reporting Canada's performance groups all departmental Strategic Outcomes and Program Activities into four broad Spending Areas: Economic Affairs, Social Affairs, International Affairs and Government Affairs.

Infrastructure Canada's one Strategic Outcome and two corresponding Program Activities align with the Government of Canada Outcomes as shown in Table 10.

Table 10: Infrastructure Canada's Linkage to the Whole-of-Government Performance Framework


2007-2008 Strategic Outcome: Improving the sustainability of our cities and communities and Canada's local, regional and national public infrastructure to enhance the economic, social, cultural and environmental quality of life of Canadians.

 

Actual Spending 2007-2008
($ thousands)

Alignment to Government of Canada Outcome Area

Budgetary

Non-budgetary

Total

Program Activity #1: Infrastructure Investments

1,943,381

0

1,943,381

Strong Economic Growth

Program Activity #2: Policy, Knowledge and Partnership Development

13,046

0

13,046

Innovative and Knowledge-based Economy


Program activity 1 contributes to the Government of Canada's "Strong Economic Growth" outcome area. By supporting modern public infrastructure, Infrastructure Canada promotes the growth and competitiveness of Canada's economy by, for example, facilitating the flow of goods and people, promoting interprovincial and international trade through gateways and corridors, supporting tourism, and increasing the use of e-commerce.

Program activity 2 contributes to the Government of Canada's "Innovative and Knowledge-based Economy" outcome area. Infrastructure Canada supports innovation and progress in delivering world-class public infrastructure and addressing priority infrastructure knowledge gaps through research, knowledge and capacity building, and strong partnerships. Based on strong cooperation with other federal departments and agencies and with partner organizations in the private sector and other jurisdictions, its work:

  • Strengthens the information base for decision-making, including improving understanding of the state and impacts of public infrastructure, identifying internal and external conditions that shape Canada's infrastructure needs, emphasizing applied research, technical excellence and sharing of best practices to increase the life expectancy of public infrastructure;
  • Improves understanding of how sound public infrastructure choices can help Canadian communities, cities and regions adapt and respond to emerging economic, environmental and social challenges, such as climate change, energy use, changing demographics, freshwater supply, and economic competitiveness;
  • Supports innovation and efficiency in the management, design, construction, operation, maintenance and rehabilitation of infrastructure, including assessment of new technologies, innovative land use, financing issues, asset management and interdependencies between asset types;
  • Measures the effectiveness of programs and infrastructure investments, new and existing systems and technologies; this includes improving performance indicators and determining the economic, social and environmental impacts of infrastructure including productivity.

For more information about the Government of Canada's four broad Spending Areas and the corresponding 13 Outcomes, visit http://www.tbs-sct.gc.ca/ppg-cpr/Home-Accueil-eng.aspx.

3.2 Federal Delivery Partners

Infrastructure Canada is part of the Transport, Infrastructure and Communities (TIC) portfolio. Infrastructure Canada collaborates with other federal departments and agencies to deliver many of its infrastructure programs; e.g., Indian and Northern Affairs Canada works with Infrastructure Canada to implement projects in the territories and those that involve First Nations in the provinces. Infrastructure Canada also works closely with Western Economic Diversification Canada, Industry Canada (Ontario), Canada Economic Development for Quebec Regions, and the Atlantic Canada Opportunities Agency.

These departments and agencies share their knowledge of local needs and priorities, as well as their technical expertise, resources and governance structures and are critical to Infrastructure Canada's ability to fulfill its mandate. For transport-related projects from the Canada Strategic Infrastructure Fund and the Border Infrastructure Fund, Transport Canada provides the federal lead role while Infrastructure Canada provides a supportive role.

In addition to federal partners, Infrastructure Canada collaborates with provincial, territorial and municipal governments and associations, as well as universities, research institutes, civil society organizations, the private sector and other experts. This collaboration is intended to:

  • Generate new, horizontal insights into infrastructure and place-based issues;
  • Develop a stronger, more multi-disciplinary research community to provide support for policy and decision makers in the multiple sectors involved in addressing Canada's infrastructure needs;
  • Gather, disseminate and communicate knowledge about infrastructure from and to key partners.

3.3 Supplementary Tables

Table 11: Comparison of Planned to Actual Spending (including FTEs)


($ thousands)

2005-2006 Actual

2006-2007 Actual

2007-2008

Main Estimates

Planned Spending

Total Authorities

Actual

Infrastructure Investments (New PAA)

 

1,455,063

2,000,322

2,859,821

3,104,822

1,942,054

Policy, Knowledge and Partnership Development (New PAA)

 

13,773

17,375

17,375

20,134

12,714

Infrastructure and Communities (Former PAA)

1,503,085

0

0

0

0

0

Crown Corporations Portfolio Management (Former PAA)

24,251

0

0

0

0

0

Total

1,527,336

1,468,836

2,017,697

2,877,196

3,124,956

1,954,768

Plus: Cost of services received without charge

2,440

2,298

 

2,004

 

1,659

Total Departmental Spending

1,529,776

1,471,134

2,017,697

2,879,200

3,124,956

1,956,427

Full Time Equivalents

180

184

N/A

237

N/A

217


Explanatory Notes:

  • The variance between total authorities and actual spending in 2007-2008 is due mainly to two factors:
    • Finalization of contribution agreements for programs such as CSIF, BIF and PT Base took longer than originally anticipated, therefore delaying the initiation of reimbursement of project claims to recipients;
    • Reduced cash requirements by recipients for the current year, based on cash flow projections for MRIF, BIF and CSIF.
  • All lapsed contribution funding in 2007-2008 will be carried forward to future years to align with recipient cash flow requirements.

Table 12: Voted and Statutory Items ($ thousands)


Vote or Statutory Item

Truncated Vote or Statutory Wording

2007-2008

Main Estimates

Planned Spending

Total Authorities

Actual

50

Operating expenditures

27,362

27,475

38,033

35,177

55

Contributions

1,988,017

2,847,403

3,084,341

1,917,009

(S)

Contribution to Employee Benefit Plans

2,318

2,318

2,582

2,582

Total Department

2,017,697

2,877,196

3,124,956

1,954,768


Table 13: Details on Transfer Payment Programs (TPPs)

Infrastructure Canada managed the following Transfer Payment Program in excess of $5 million:

  • Contributions under the Canada Strategic Infrastructure Fund;
  • Contributions under the Border Infrastructure Fund;
  • Contributions under the Municipal Rural Infrastructure Fund;
  • Transfer Payments under the Gas Tax Fund.

For further information on the above-mentioned transfer payment programs see: http://www.tbs-sct.gc.ca/dpr-rmr/st-ts-eng.asp.

Table 14: Reporting on Horizontal Initiatives

The objective of reporting on Horizontal Initiatives is to provide Parliamentarians, the public and the government with an overall picture of public expenditures, plans, priorities and achievements for all major horizontal initiatives.

A Horizontal Initiative is an initiative in which partners from two or more organizations have agreed, under a formal funding agreement, to work towards the achievement of shared outcomes. Over the last year, Infrastructure Canada led four horizontal initiatives: Canada Strategic Infrastructure Fund, Border Infrastructure Fund, Municipal Rural Infrastructure Fund and Infrastructure Canada Program.

Supplementary information on the above-mentioned Horizontal Initiatives can be found at http://www.tbs-sct.gc.ca/rma/eppi-ibdrp/hrdb-rhbd/profil_e.asp.

Table 15: Internal Audits Completed in 2007-2008


Name of Internal Audit

Audit Type

Status

Completion Date

Financial Management Control Framework Components of Stewardship and Accountability

Financial management controls

Completed

November 2007

Financial Coding

Financial management controls

Completed

November 2007

Monitoring of the Operating Budget

Financial management controls

Completed

March 2008

Departmental Delegation of Financial Authority

Follow up

Completed

March 2008

Human Resources Classification and Staffing

Human Resources

In progress

May 2008 (expected)


Table 16: Evaluations Completed in 2007-2008


Program

Name of Evaluation

Description

Approval date of the evaluation framework

Start date of field work

Approval date of the final report

MRIF

Formative evaluation of MRIF

The formative (or interim) evaluation of MRIF assessed results achieved to date on the Program and also included a review of issues related to the implementation and administration of the Program (design and delivery issues).

Sept. 2006

June 2007

March 2008

GTF

Process evaluation of the GTF (Implementation Review)

Internal formative/process evaluation was carried out to assess the implementation of the initiative and to ensure that the management and reporting systems have been set up properly.

Jan. 2007

Nov. 2007

March 2008