Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.
The Grants and Contributions Delivery Project (GCDP) is being repositioned to ensure that it complies with the Department's overall grants and contributions reform, supports Government of Canada administrative reform efforts, and so that rigorous project management controls required for projects of this size are implemented.
GCDP received authority in June 2009 through the Growing Forward Service Excellence Initiative to conduct Phase I - Preliminary Project Approval (PPA) of GCDP, which includes the System Development Life Cycle phases of Conceptual, Preliminary and Detailed Design.
In Phase II, the GCDP will perform business alignment of programs through the adoption of common business processes, as well as the implementation of a common technical platform. Both will improve the access, management and delivery of non-BRM Grants and Contributions (Gs&Cs) programs.
The GCDP is split into two discrete phases:
The project will officially conclude when:
This project is currently in the initiation, planning and design phase.
Lead Department | Agriculture and Agri-Food Canada |
---|---|
Contracting Authority | Agriculture and Agri-Food Canada, Public Works and Government Services Canada |
Participating Departments | Public Works and Government Services Canada, Treasury Board Secretariat |
Prime Contractor | Deloitte & Touche LLP - 100 Queen Street, Suite 800, Ottawa, Ontario, K1P 5T8 |
---|---|
Major Subcontractor(s) | CSDC Systems Inc. (formerly Grantium) - 279 Laurier Ave. West, Suite 200,Ottawa, Ontario K1P 5J9 |
List of Major Milestones | Completion / Target Date |
---|---|
Preliminary Project Approval | 04-Jun-2009 |
Conceptual Design & Approved Architecture | 01-Jul-2010 |
Business Alignment | 31-Mar-2011 |
Detailed Design | 31-Mar-2011 |
Treasury Board Submission (Final Draft) | 01-Jan-2011 |
Treasury Board Submission Approval | 31-Jan-2011 |
Development and Implementation | 30-Nov-2012 |
Stabilization and Maintenance | 31-Mar-2013 |
Progress to date:
Conceptual Design - Complete
Preliminary & Detailed Design - Complete
Overall Business Requirements - Complete
Supplementary Project Staffing - Complete
Pre-Phase II Health Check Independent Review (to assess the viability of the GCDP go forward plan and the project’s readiness to proceed) - Complete
Management Response to Independant Assesment and associated Action Plan - Complete
Project Governance - Complete
Business Transformation - Under way
Phase II Treasury Board Submission (Authority to proceed with Business Transformation and the Development and Implementation of the GCDP) - Under way
The project team has re-established project milestones target dates for the PPA phase of the project to ensure the business re-design is achieved before implementing technology. This will ensure a stronger understanding and endorsement of Gs&Cs reform and the proposed solution department wide, which will form the basis for Phase II being submitted to Treasury Board. The GCDP team developed a strategy and has addressed all findings of the independent assessment and has identified an approach to stay aligned to the Service Excellence Treasury Board Submission to have a common non-BRM Gs&Cs delivery platform implemented by 2013.
In February 2007, an independent blue ribbon panel provided recommendations aimed at simplifying the administration of Gs&Cs while, at the same time, strengthening accountability and risk-based approaches for managing the programs. Through the development of the action plan and other work that has taken place over the past year, AAFC is meeting the commitments made by the Government in response to the panel's key recommendations.
With this plan, recipients, stakeholder organizations and federal program administrators will be able to see AAFC's progress, and more importantly, the project's next steps and the Department's commitment to engage them in the process. The last year has seen much activity, and a solid foundation is being laid for systemic change. This kind of change takes time, and there is still much work to be done. However, it is believed that the action plan will serve as a vital roadmap to guide AAFC over the next few years.
Note: Further details on this project can be found in the Status Report on Projects operating with specific Treasury Board Approval in the 2009-10 Departmental Performance Report.