Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.


Table 3-6: Details on Project Spending (millions of dollars)

 

2007-08

Program Activity

Current Estimated Total Cost

Actual 2005-06

Actual 2006-07

Total Main Estimates

Total Planned Spending

Total Authorities

Actual

 

 

 

 

 

 

 

 

Research and Development

 

 

 

 

 

 

 

Advanced Aerospace Manufacturing Technology Centre, Project Close-out Phase, (S-EPA)

34.1

0.4

-

-

-

-

-

Aluminium Technology Centre, Project Close-out Phase, (S-EPA)

34.4

2.5

 

7.8

7.8

7.8

7.8

Construction of the Canadian Photonics Fabrication Centre, Project Close-out Phase, (S-EPA)

19.0

1.1

-

6.2

6.2

6.3

6.3

Construction of an Industrial Partnership Facility (IPF) adjacent to NRC-IBD, Project Close-out Phase, (S-EPA)

11.0

1.7

-

0.1

0.1

0.1

0.1

Move of the National Research Council's Innovation Centre, Project Close-out Phase, (S-EPA)

18.7

13.1

1.6

0.0

0.0

0.0

0.0

Construction of Industry Partnership Facility (IPF) at NRC-IMB, Project Close-out Phase, (DA)

7.2

0.5

-

0.1

0.1

0.1

0.1

Lease Project Approval for the National Institute for Nanotechnology, Project Implementation Phase (I-LPA)

87.2

5.4

2.4

1.3

1.3

1.3

1.3

Lease Project Approval for the Institute for Nutrisciences and Health, Project Implementation Phase (I-LPA)

20.9

-

0.3

0.5

0.5

0.5

0.5

 

Notes

  • Due to rounding, figures may not add to total shown.