Archived [2022-03-02] - Directive on the Management of Projects and Programmes

The directive ensures that government projects and programmes are effectively planned, implemented, monitored, controlled and closed, so that the expected benefits and results are realized for Canadians.
Date modified: 2019-05-13

Supporting tools

Mandatory procedures:

Archives

This directive is replaced by:

View all inactive instruments
Print-friendly XML

While the requirements in the Directive on the Management of Projects and Programmes, including the mandatory procedures and appendices, take effect on , with the exception of the requirements of 1.3 and 1.4, departments have six months to fully transition to the new directive.

With respect to requirement 1.4, projects approved under the Policy on the Management of Projects or the rescinded Project Approval Policy prior to , have until , to transition to the Directive on the Management of Projects and Programmes.

Appendix A: Mandatory Procedures for Organizational Project Management Capacity Assessments

A.1 Effective date

  • A.1.1These procedures take effect on .
  • A.1.2These procedures replace the following Treasury Board policy instruments:
    • Standard for Organizational Project Management Capacity Assessments()

A.2 Procedures

  • A.2.1These procedures provide details on the requirement set out in section 4.1.10 of the Directive on the Management of Projects and Programmes.
  • A.2.2Mandatory procedures are as follows:
    General requirements
    • A.2.2.1All departments seeking an increase to the base project approval authority limit of $2.5 million must do so using the Organizational Project Management Capacity Assessment (OPMCA).
    What the assessment covers
    • A.2.2.2The assessment measures the capacity of a department to successfully deliver a defined volume of work over a fixed period of time.
    • A.2.2.3The generally accepted method to establish this volume of work is to prepare a list of all planned and active projects of $2.5 million and greater, covering the period of time for which the requested authority will be in effect.
      • A.2.2.3.1If this is not practicable, the department must meet with TBS in advance of starting the OPMCA and confirm how the volume of work will be established and communicated.
    Evidence in support of the OPMCA
    • A.2.2.4TBS must be consulted at the start of the process to confirm the evidence that will be used to support the OPMCA;
    • A.2.2.5 Sources of evidence must include:
      • A.2.2.5.1A representative sample of recent projects;
      • A.2.2.5.2 Findings from the past three years of internal or external audits, evaluations, reports, or other findings addressing the departments project management capacity; and
      • A.2.2.5.3Treasury Board conditions from the past three years pertaining to project management capacity.
    Submitting the OPMCA
    • A.2.2.6Submit the draft OPMCA, with its evidence, to TBS for review.
    • A.2.2.7Revise, if necessary, the OPMCA based on TBS's feedback.
    • A.2.2.8Submit the deputy head–approved final OPMCA to TBS through the approved centralized application.
    • A.2.2.9Prepare the Treasury Board submission to seek approval of the Organizational Project Management Capacity Assessment Class.
    Changes in Organizational Project Management Capacity Assessments
    • A.2.2.10Inform TBS in a timely manner of any significant changes to the organizational project management capacity that may affect the Treasury Board approved capacity class.
    • A.2.2.11If requested by TBS, revise the OPMCA.

A.3 References

  • Guide to Using the Organizational Project Management Assessment Tool
  • Organizational Project Management Assessment Tool