<?xml version="1.0" encoding="ISO-8859-1"?><doc title="Rescinded - Project Approval Policy" documentID="12075" versionID="1" language="en" space="preserve" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:noNamespaceSchemaLocation="PolicySchema.xsd"><notetoreader><div>
  On April 1, 2012, this policy will be replaced by the <em><a href="/pol/doc-eng.aspx?id=18229">Policy on the Management 
  of Projects</a></em> for departments and agencies listed in Section 2 of the <em><a href="http://laws-lois.justice.gc.ca/eng/acts/F-11/">Financial Administration Act</a></em>. Treasury Board Secretariat 
  is adopting a phased implementation approach, starting in 2007, that will begin with a group of departments that have 
  agreed to participate in a pilot. Following this pilot, groups of departments will be brought on board so that, by April 
  1, 2012, departments and agencies will have the systems and processes in place to meet the policy requirements.
</div></notetoreader><chapters><chapter anchor="1" title="Policy objective"><p>To ensure that projects proposed for approval, by the sponsoring Minister or, where required, by the Treasury Board can 
receive informed and effective consideration.</p></chapter><chapter anchor="2" title="Policy statement"><p>It is government policy that:</p><ul><li>Treasury Board approval for capital, lease and information technology projects be sought where:<ul><li>the total estimated cost of the project exceeds the level that the sponsoring Minister can approve;</li><li>during implementation, the projected costs to complete the project exceed, either the level that the sponsoring 
    minister can approve or the limits previously approved by the Treasury Board; or</li><li>there has been a significant change to the baseline established in the initial Treasury Board approval of the project.</li></ul></li><li>All projects submitted for approval be supported by documentation that adequately describes the full scope of the 
  project including the associated management framework; and,</li><li>All projects proposed for approval be reviewed to ensure that they represent an effective and efficient solution to 
  the operational needs as set out in the department's defined priorities or in the Long-term Capital Plan (LTCP).</li></ul></chapter><chapter anchor="3" title="Application"><p>This policy applies to departments listed in Schedules I and II of the <em>Financial Administration Act.</em></p><p>The policy applies to <em>projects</em> and to <em>capital, lease and information technology projects</em> as defined 
in the Glossary of this volume. It applies to all such projects funded in whole or in part by the federal government regardless 
of the method of acquisition.</p><p>The Treasury Board may designate any collection of activities as a capital project for the purposes of this policy.</p><p>This policy does not apply to certain project-like activities funded by the federal government through transfer payments 
(grants or contributions). Treasury Board policies on financing, managing and approving these activities are provided in 
the Financial Management volume of the <em>Treasury Board Manual.</em></p></chapter><chapter anchor="4" title="Policy requirements"><ol><li><strong>Identification:</strong> Departments must identify collections of activities that constitute <em>projects</em> 
	under this policy and manage them accordingly.</li><li><strong>Cost-effectiveness:</strong> All project proposals must clearly reflect a cost-effective approach to meeting 
	the operational needs set out in the LTCP or other appropriate departmental documentation.</li><li><strong>Process:</strong> To ensure projects are planned and executed in a timely and effective manner, departments 
	must institute an efficient project approval and review process.</li><li><strong>Approval authority:</strong> The approval authority will establish an agreed upon project baseline when approving 
	the project. Any significant deviations from this baseline must be authorized by the appropriate approval authority.</li><li><strong>Project scope:</strong> All project proposals must be supported by appropriate documentation that describes 
	the scope of the project in terms of such elements as key deliverables, phasing to manage risk, timing, contracting strategy, 
	special requirements, and project management. When departments have already prepared project briefs, these will constitute 
	appropriate documentation.</li><li><strong>Project phases:</strong> To provide for adequate departmental approval and control, project implementation 
	must be broken down into phases corresponding to natural decision points. Chapters 2-2 and 2-3 of this volume provide guidance 
	on this and other project management matters.</li><li><strong>Treasury Board approval:</strong> The department must obtain Treasury Board approval for a capital project 
	(including leases and information technology projects) when the total estimated cost exceeds the level that the sponsoring 
	Minister can approve (see Appendix E). Only those specific phases of the project that have been appropriately defined and 
	costed can be approved.</li><li><strong>Proposals:</strong> There are three types of proposals that may be submitted for Treasury Board approval.
		<ul class="noBullet"><li>8.1 Normally, the first submission by a department seeks Preliminary Project Approval (PPA) and authority to proceed 
			with all or part of the project's definition phase. To support a proposal for PPA, departments must clearly demonstrate 
			that a requirement directly related to the achievement of program goals and responsibilities exists, and that the design 
			and implementation of the proposed project best meet that requirement. Requirements for a PPA are further described in Appendix 
			A.</li><li>8.2 When the project is fully defined, the department submits for Effective Project Approval (EPA) to obtain authority 
			to implement the project. Approval of EPA also establishes the cost and other critical objectives that form the project 
			baseline. Appendix B provides detailed requirements for an EPA submission.</li><li>8.3 Projects that mainly involve leasing require a Lease Project Approval (LPA), before bids can be solicited. The LPA 
			effectively combines PPA and EPA into a single approval process. Appendix C provides detailed requirements for an LPA.</li></ul></li><li><strong>Single submission:</strong> Some projects do not require an extensive project definition phase. In these cases, 
	departments may seek only EPA. This single submission must provide the information required in both PPA and EPA submissions.</li><li><strong>Omnibus submissions:</strong> Departments may group several related projects together in omnibus submissions. 
	Departments may also, when appropriate, request PPA, EPA, or LPA through the LTCP or through the Multi-Year Operational 
	Plan.</li><li><strong>Information technology projects:</strong> Information technology projects must be developed and implemented 
	in conformance with the Information Management policy and the strategic directions that have been established by the government. 
	Appendix D details specific submission requirements for information technology projects. Further information on requirements 
	for information technology projects may be obtained in the Information Management volume of the <em>Treasury Board Manual</em> 
	or by contacting the Office of Information Management, Systems and Technology, Treasury Board Secretariat.</li><li><strong>Project brief:</strong> This is a detailed description of the project, including its scope. It shows the 
	relationship of the project to departmental priorities and the LTCP. In addition, the project brief summarizes the analysis 
	of the options that were considered and why the proposed project is the preferred solution. It also provides an overview 
	of the project management framework. A project brief must accompany all submissions for Major Crown projects; all other 
	projects must be supported by either a project brief or other appropriate documentation that meet the requirements of Appendices 
	A through D. Appendix F provides the detailed requirements for a project brief.</li><li><strong>Cost overrun:</strong> A project is in a cost overrun condition when the current "estimate at completion" 
	exceeds the currently approved cost objectives, without any corresponding changes in the scope of the project. If the total 
	estimated cost of the project then exceeds the level that the sponsoring Minister can approve, the department must submit 
	the project for Treasury Board approval. If Treasury Board EPA had been provided, a revised EPA would be required.</li><li><strong>Financial information:</strong> Departments must provide project information in their Departmental Performance 
	Report and Report on Plans and Priorities in accordance with the Departmental Performance Reports Preparation Guide and 
	the Guide to Preparation of the Report on Plans and Priorities.</li></ol></chapter><chapter anchor="5" title="Monitoring"><p>Treasury Board Secretariat will use the following criteria to assess departmental performance in meeting the objectives 
of this policy:</p><ul><li>consistency between projects proposed for approval and strategies contained within a Treasury Board considered LTCP 
  as well as other government objectives;</li><li>timeliness of Treasury Board submissions for project approval;</li><li>compliance with the information requirements provided for in this policy, including the quality of the information 
  included in Treasury Board submission. Quality is considered to cover such aspects as completeness, accuracy and ease 
  of understanding. Particular attention will be given to the Options analysis, the description of the project scope and 
  cost estimates.</li></ul></chapter><chapter anchor="6" title="References"><p>This policy is issued under the authority of section 7 of the <em>Financial Administration Act.</em> This policy replaces 
the project approval portions of Chapter 540 of the <em>Administrative Policy Manual,</em> and TB Circular 1983-25, May 
1, 1983, <em>Approval of Capital Projects and Long-term Capital Plans.</em></p><p>This policy should be read with the other chapters in this volume and other policies, particularly those dealing with 
risk management, materiel management, real property, information technology management, contracting and common services 
organizations.</p></chapter><chapter anchor="7" title="Enquiries"><section anchor="7.1" title="Policy requirements"><p>For enquiries related to policy interpretations, contact the Executive Director, Procurement and Project Management Policy 
Directorate, Comptrollership Branch, Treasury Board Secretariat.</p></section><section anchor="7.2" title="Treasury Board submissions"><p>For questions about Treasury Board submissions and departmental program matters, departments should contact their analyst 
within the TBS Program Sectors and, as appropriate, their specialist analyst in the Real Property and Materiel Policy Directorate, 
or the Chief Information Officer Branch.</p></section></chapter></chapters><appendices><appendix anchor="A" title="Appendix A - Requirements for Treasury Board Submissions Seeking Preliminary Project Approval (PPA)"><section anchor="A.1" title="Introduction"><p>Definitions of the terms used in this appendix are provided in the Glossary of this volume.</p><p>Departments normally request PPA when the initial project planning and identification phase is completed 
but before the project definition phase starts. The formal Treasury Board approval process may be tailored to individual 
projects and departments, depending on the nature of the risks involved in those projects. Departments should plan and coordinate 
submissions for approvals to minimize administrative overhead.</p><p>In providing PPA, Treasury Board ministers agree that a program requirement has been identified and 
there is adequate justification for meeting that requirement through a particular project. PPA also provides authorization 
to expend resources to fully define the selected project option.</p><p>The PPA submission must be prepared in accordance with the Treasury Board Submissions Guide volume 
of the <em>Treasury Board Manual </em>and must include information for each section as follows.</p></section><section anchor="A.2" title="Proposal"><p>1. The proposal must list all authorities being sought from the Treasury Board, and include:</p><p>1.1 the cost objective for the project definition phase, which will establish the total amount of funds 
approved by the Treasury Board for the purposes of defining the project. The cost objective refers to the substantive cost 
estimate (as defined in Appendix G to this chapter) for the project definition phase and must include such provisions as 
the costs of employee benefit plans (20 percent of salaries) for all salaries charged to the project and normal contingencies 
such as for inflation and foreign exchange. For multi-year undertakings, costs must be expressed in both constant and current 
dollars; and,</p><p>1.2 all other objectives that have been deemed by the department, in consultation with the Treasury 
Board Secretariat, to be sufficiently critical to require specific authority by the Treasury Board.</p><p>2. Once approved, these objectives will serve as the project baseline for monitoring by the Treasury 
Board.</p></section><section anchor="A.3" title="Supporting Documentation"><p>3. This information is included in either the body of the submission or the project brief, when appropriate.</p><p>3.1 The background section identifies a program requirement and provides justification that it 
is directly related to the department's goals and responsibilities and can be addressed through the effective design and 
implementation of the appropriate project.</p><p>3.2. The total project cost estimate provides an indicative estimate (as defined in Appendix 
G to this chapter) of the total cost and annual cash flow estimate for the overall project.</p><p>3.2.1 The indicative estimate will be refined and improved as the project definition phase proceeds.</p><p>3.2.2 This estimate is provided to Treasury Board ministers for information and is not in any 
way approved by the Board. It is an important consideration as to whether or not PPA will be granted and as such, departments 
should ensure that the estimate is as accurate as possible at the time they request PPA.</p><p>3.2.3 Overall project costs as indicated in the PPA submission may differ in the subsequent EPA 
submission. If, at the time departments request EPA, the estimated project costs significantly exceed the indicative estimates 
in the PPA submission, the options analysis must be reviewed to ensure that the selected option continues to represent the 
most cost-effective approach to fulfilling the requirements. An exception to this general concept is that the Treasury Board, 
as part of the PPA approval, may wish to impose a "cap" or other constraint on the project. This would force the project 
to use a "design-to-cost" approach during the project definition phase.</p><p>3.3 The overall project schedule provides an estimated milestone schedule for the overall project.</p><p>3.4 The summary of comprehensive cost-benefit and options analyses provides information on the 
options the department has considered and the current status of the recommended option at the time of submission. The detailed 
analysis, normally incorporated into the project brief, must be based on the fully defined statement of requirement and 
the life-cycle costing of the asset for each option examined. If the detailed analysis is available in a project brief, 
the submission itself will provide an outline of the options reviewed and justification for the option that has been chosen.</p><p>3.5 The risk assessment section provides the results of the risk assessment conducted for the 
selected option and a separate assessment for the project definition activity when expenditure authority is being sought. 
The level of detail of the project risk assessment is to be appropriate for the type of the project. Guidance for project 
risk assessment and management is provided in Appendix C of the Project Management policy, of this volume.</p><p>3.6 The project management approach section provides a summary of the proposed management approach. 
This approach must be consistent with the project management chapters of this volume.</p><p>3.7 The outstanding issues section provides an assessment of any current issues and includes 
proposals for the resolution of all outstanding issues.</p><p>3.8 If any of the following objectives are deemed by the department, in consultation with the 
Treasury Board Secretariat, to be essential to the success of the project, they should be included in the formal proposal:</p><p>3.8.1 schedule objective providing the proposed start and completion dates as well as any critical 
milestone dates for the project definition phase; and,</p><p>3.8.2 performance objective defining the proposed major outputs or deliverables for the project 
definition phase.</p><p>3.9 The procurement strategy for the whole project, as detailed in chapters 3-1 and 3-2 of this 
volume, must be included if appropriate.</p><p>4. Other sections may be required in the submission to cover such topics as industrial, regional or 
other national benefits, administrative requirements, possible international or other agreements and a communications plan.</p></section><section anchor="A.4" title="Approval"><p>5. Treasury Board approval of the PPA will be in the form of a decision letter. The letter may include 
changes to the proposed objectives as well as other direction from the Treasury Board. Proposed deviations from what has 
been approved by the Treasury Board should be discussed with the Treasury Board Secretariat at the earliest opportunity 
to assess whether an amended authority is required.</p><p>6. The department is accountable to the Treasury Board for meeting the established baseline and any 
other directions set out in the decision letter. Appropriate internal accountabilities apply for the delivery of all aspects 
of the project not specifically approved by the Treasury Board.</p></section></appendix><appendix anchor="B" title="Appendix B - Requirements for Treasury Board Submissions Seeking Effective Project Approval (EPA)"><section anchor="B.1" title="Introduction"><p>Definitions of the terms used in this appendix are provided in the Glossary of this volume.</p><p>Departments submit for EPA before starting the project implementation phase. For those projects where 
the Treasury Board has not provided a PPA, the EPA must include all information required for PPA. The formal Treasury Board 
approval process may be tailored to individual projects and departments, depending on the nature of the risks involved in 
those projects. Departments should plan and coordinate submissions for approvals to minimize administrative overhead.</p><p>The EPA submission is to be prepared in accordance with the Treasury Board Submissions Guide of the
<em>Treasury Board Manual</em> and must include information for each section as follows.</p></section><section anchor="B.2" title="Proposal"><p>1. The proposal must list all the Treasury Board authorities being sought, including approval for implementing 
a particular project.</p><p>2. The proposal must include the cost objective for the project implementation phase.</p><p>2.1 The cost objective refers to the substantive estimate (as defined in Appendix G) of the total resources 
to be approved by the Treasury Board for implementing the project.</p><p>2.2 For multi-year undertakings, costs must be expressed both in constant and current dollars and must 
include, the costs of employee benefit plans (20 percent of salaries) for all salaries charged to the project, the costs 
for government project management and normal contingencies such as for inflation and foreign exchange.</p><p>3. The proposal must also include any other objectives that have been deemed by the department, in 
consultation with the Treasury Board Secretariat, to be sufficiently critical to require specific authority by the Treasury 
Board.</p><p>4. Once approved, these objectives will serve as a project baseline for monitoring by the Treasury 
Board.</p></section><section anchor="B.3" title="Supporting Documentation"><p>5. This information is included in either the body of the submission or the project brief, when appropriate.</p><p>5.1 The outstanding issues section provides a final assessment of issues that were outstanding at any 
previous stage of the Treasury Board's consideration of the project, as well as any current issues. It must include proposals 
for resolving all outstanding issues.</p><p>5.2 A section which provides further cost information supporting the cost objective included in the 
proposal. Project cash flow estimates must be included for information purposes. The cost estimate must include separate 
line items for major risk factors. This is used to inform the Treasury Board of potential future expenditures that might 
be difficult to avoid without abandoning the project.</p><p>5.3 The formal risk assessment section provides an updated formal risk assessment for the overall project.</p><p>5.4 The project management approach provides the Treasury Board with the necessary assurances that 
the department has appropriate project accountability, control and management systems in place to monitor the project's 
progress and react to changing circumstances. The definition of these systems must be consistent with the project management 
policies of this volume.</p><p>5.5 A description of agreements which provides full details of agreements for international cooperation, 
federal-provincial arrangements or agreements with other government departments. The description must distinguish between 
existing agreements that affect the project and agreements entered into specifically to further the project or required 
before progress can be made. Copies of agreements and similar documents must accompany the project submission.</p><p>5.6 The administrative requirements section describes the possible impact of the project resulting 
from existing or potential legislation, policy issues that may arise (including procurement policy when relevant), or organizational 
or procedural changes required for or resulting from the project.</p><p>5.7 A communications plan must accompany the submission whenever the project is likely to attract public 
attention that will require a response from the government.</p><p>5.8 A detailed project objectives section. When, in consultation with the Treasury Board Secretariat, 
any of these objectives are deemed to be sufficiently critical to warrant specific approval and ongoing consideration by 
the Treasury Board, they should be included in the formal proposal. Possible project objectives include:</p><p>5.8.1 a schedule objective, providing the proposed start date, critical schedule dates and completion 
date of the implementation phase, supported by the planned time-phasing of the work. The schedule takes into account any 
time required for the contracting process itself;</p><p>5.8.2 a performance objective, describing the proposed major outputs or deliverables of the project. 
If work is to be performed by private contractors, a description of the deliverables and their relationships to subsequent 
phases of the project must be included;</p><p>5.8.3 an industrial and regional benefits objective, describing (when applicable) the proposed industrial 
benefits to be achieved during the project's implementation. The objective is to be expressed in quantitative terms, as 
established during procurement review or through other interdepartmental consultations and agreements; and,</p><p>5.8.4 other national objectives, describing (when applicable) other agreed objectives to be achieved 
during the project's implementation. When feasible, these objectives are to be expressed in quantitative terms, as established 
through interdepartmental consultations and agreements.</p><p>5.9 Departments must estimate future ongoing operating and maintenance expenditures directly attributable 
to the implementation of the project, including grants-in-lieu of taxes. Departments must also indicate a source of funds 
for these costs. The purpose of providing this information is to ensure that there will be appropriate funding available 
to operate or maintain the deliverables once the project is completed.</p></section><section anchor="B.4" title="Approval"><p>6. Treasury Board approval of the EPA will be in the form of a decision letter. The letter may include 
changes to the proposed objectives as well as other direction from the Treasury Board. Proposed deviations from what has 
been approved by the Treasury Board should be discussed with the Treasury Board Secretariat at the earliest opportunity 
to assess whether an amended authority is required.</p><p>7. The department is accountable to the Treasury Board for meeting the objectives and any other directions 
set out in the decision letter. Appropriate internal accountabilities apply for the delivery of all project objectives not 
specifically approved by the Treasury Board.</p></section></appendix><appendix anchor="C" title="Appendix C - Requirements for Treasury Board Submissions Seeking Lease Project Approval (LPA)"><section anchor="C.1" title="Introduction"><p>Definitions of the terms used in this appendix are provided in the Glossary of this volume.</p><p>When the present value of a project that is predominantly lease-related exceeds the minister's authority 
level, the department must obtain an LPA before soliciting bids. The LPA effectively combines the PPA and EPA submissions 
into a single approval process.</p><p>The submission must be made early in the planning phase so that realistic options are available to 
decision makers. It is therefore, similar to a PPA submission. The LPA submission must also contain information based on 
market prices and clear assumptions regarding likely costs to adapt the leased asset to operational requirements. The formal 
Treasury Board approval process may be tailored to individual projects and departments, depending on the nature of the risks 
involved in those projects. Departments should plan and coordinate submissions for approvals to minimize administrative 
overhead.</p><p>The LPA submission is to be prepared in accordance with the Treasury Board Submissions Guide volume 
of the <em>Treasury Board Manual</em> and must include information for each section as follows.</p></section><section anchor="C.2" title="Proposal"><p>1. The proposal must list all authorities being sought from the Treasury Board to implement the Lease 
Project Approval.</p><p>2. The proposal must include a substantive cost estimate objective (see Appendix G), for a lease project, 
of a specific total value.</p><p>2.1 The cost objective must include an estimate of the anticipated cost of the lease arrangement. The 
estimate must include the expected cost per metre squared of usable space and the net present value of the net rental costs 
of the lease period. It must also include all anticipated costs for construction (fit-up and building improvement), commissioning, 
design, moving and any other one-time costs associated with bringing the property into inventory. This includes fees, registration 
costs and any taxes.</p><p>2.2 The costs shown in an LPA should be based on market comparable since the actual costs won't be 
known until a lease is solicited and negotiated.</p><p>2.3 For the purposes of the LPA, lease option periods must be excluded from both the cost estimates 
and authorities being sought. However, full disclosure is to be made to the approving authority of the options that are 
intended to be sought and that will be considered in the selection or evaluation state. The exercising of options will be 
treated as a separate project for approval purposes.</p><p>2.4 After the receipt of offers, when a lease contracting authority is sought from Treasury Board for 
approval, the overall project costs from the lease project approval (LPA) submission must be revised, as appropriate, to 
reflect actual costs. A revised LPA is required if the cost exceeds the original LPA cost or if project costs are no longer 
consistent with the original purpose and quality level quoted in the LPA.</p><p>3. The operating and maintenance costs and property taxes that will be associated with or included 
in the lease contract, while not part of the project costs, must be provided for information purposes in order to identify 
the full costs associated with the project.</p></section><section anchor="C.3" title="Supporting Documentation"><p>4. This information may be included in either the body of the submission or in an accompanying investment 
analysis report.</p><p>4.1 The background section identifies the program requirement for the leased space and provides justification 
that it can be addressed by the proposed project.</p><p>4.2 The cost information section demonstrates how the costs (market comparable) were established.</p><p>4.3 The timing section indicates the critical milestones for the project, including the timing of lease 
solicitation, contract approval, fit-up, base requirements and tenancy.</p><p>4.4 A summary of the various options must be outlined. This includes both other lease options that 
could meet the program requirements and other acquisition strategies such as construction by the Crown. The cost and program 
implications of each option must be noted.</p><p>4.5 The assumptions, risks and uncertainties section outlines the assumptions that have been made about 
the market and the risks and uncertainties inherent in the proposed lease project approach. It should also indicate the 
steps that have been taken to manage these factors.</p><p>4.6 The outstanding issues section provides an outline of any other issues that require resolution 
before the bid can be solicited or negotiated.</p></section><section anchor="C.4" title="Approval"><p>5. Treasury Board approval of the lease project will be in the form of a decision 
letter. The letter may include changes to the proposed objectives as well as other direction from the Treasury Board. The 
department is accountable to the Treasury Board for meeting the project objectives and any other directions set out in the 
decision letter.</p></section></appendix><appendix anchor="D" title="Appendix D - Requirements for Treasury Board Submissions for Information Technology Projects"><section anchor="D.1" title="Introduction"><p>The purpose of this appendix is to outline requirements that are particular to submissions for information technology 
projects.</p></section><section anchor="D.2" title="Submission requirements"><p>In general, the information requirements outlined in appendices A and B must be followed, with the modifications noted 
below.</p><p>1. Demonstrated compliance with government-wide strategies: Through appropriate documentation, departments must 
demonstrate that the proposal satisfies the strategic directions that the government has adopted for information technology. 
These include:</p><p>1.1 Enhancing services through the innovative use of information and technology: There are five major objectives 
in this area: renewing services and program delivery; investing strategically; building partnerships; building an open architecture 
and core infrastructure; and distributing computer power to managers and staff;</p><p>1.2 Architecture - standards: Departments must have transition plans for conforming to information technology standards 
as referenced in an open systems environment model that defines a technical framework or architecture for the development 
of computer and communications systems in the federal government. This model encompasses the strategic directions of Open 
Systems Interconnection (OSI), Electronic Service; Portability of Applications; and enterprise-wide Open Systems. The technical 
approach in the project must comply with Treasury Board Information and Technology Standards (TBITS), which should be quoted 
in procurement requests; and,</p><p>1.3 Mandate of the Chief Informatics Officer: All information technology projects must be consistent with government-wide 
policies, strategies and technology standards. These policies, strategies and standards aim to improve how government deliver 
services using information technology. They also provide a basis for the development of more efficient administrative processes 
in government. Functional direction will be provided by the CIO on interdepartmental projects and cross-government initiatives, 
such as administrative systems and telecommunications. Additionally, the CIO has issued a draft Blueprint for the re-engineering 
of government service delivery through improved use of information technology.</p><p>2. Departmental plans: The approach taken in the project must be consistent with the department's strategies identified 
in its information management plan. The proposed strategies will protect investments, foster interoperability and allow 
competition among suppliers.</p><p>3. Use of business case methodology: The business-case approach is the required methodology for identifying, justifying 
and selecting information technology projects for investments. This approach relates specific project proposals to departmental 
information technology strategies and plans in the context of program priorities and measurable improvements in program 
performance.</p><p>4. Costs: For either PPA or EPA, costs relate to project cost only. All direct costs should be identified, including 
all departmental resources involved in designing, developing and acquiring software; all implementation aspects (eg. documentation, 
training, testing and installation), as well as the cost of acquiring the information technology hardware.</p><p>5. Project brief: In most instances, a project brief will be required to explain the complexities of the business case 
and of the systems development. Additional information on the project brief is provided in Appendix F.</p><p>6. Human resource strategy: Information technology projects will usually have significant impacts on job requirements, 
training and staff deployment. The submission must include an analysis of the human resource impact of the proposed project 
and the departmental strategies for addressing these impacts. Such strategies would normally include a plan for consulting 
with unions and affected personnel.</p><p>7. Other related legislation and policies: Proposed projects must demonstrate compliance with the following:</p><p>7.1 Security requirements: These must be reviewed early in the project. For guidance on technical security features, 
consult Treasury Board Information and Technology Standards (TBITS) 6.6, Security Profile. This profile provides a linkage 
to the Canadian Government Information Technology (I.T.) Security policy, standards, and guidelines; and, provides guidance 
on the implementation of secure interoperable systems.</p><p>7.2 Information management and privacy: The project must adhere to government policy and departmental practices for information 
management and the collection and use of personal information.</p><p>8. Funds: Departments must provide information on operating and maintenance expenditures covering a five-year period 
following project implementation. Departments must also indicate a source of funds for these expenditures. The purpose of 
providing this information is to ensure that there will be appropriate funding available to operate or maintain the deliverables 
once the project is completed.</p><p>Further information on specific requirements for information technology projects may be obtained from the Information 
Management volume of the <em>Treasury Board Manual</em> or by contacting the Office of Information Management, Systems and 
Technology.</p></section></appendix><appendix anchor="E" title="Appendix E - Departmental Approval Authorities"><p><strong>Note:</strong> This is a compilation of authority limits provided specifically by Treasury Board to individual 
ministers. This compilation is provided for information only.</p><table border="1" cellspacing="0" class="widthFull" summary="Appendix E - Table of Departmental Approval Authorities"><tr class="lightgreyBG alignMiddle"><th rowspan="2" scope="col"><strong>Department/Agency</strong></th><th scope="colgroup" colspan="2"><strong>Real Property</strong></th><th scope="colgroup" colspan="2"><strong>Information Technology</strong></th><th scope="col" rowspan="2"><strong>All Other Projects</strong></th></tr><tr class="alignTop"><th scope="col"><strong>General</strong></th><th scope="col"><strong>Special</strong></th><th scope="col"><strong>New</strong></th><th scope="col"><strong>Replacement</strong></th></tr><tr class="alignTop"><td>Agriculture and Agri-Food Canada<br />
      Prairie Farm Rehabilitation Administration</td><td><p class="alignRight">$5M</p></td><td><p class="alignRight">$15,000</p></td><td><p class="alignRight">$5M</p></td><td><p class="alignRight">$10M</p></td><td><p class="alignRight">$1M</p></td></tr><tr class="alignTop"><td>Canada Customs and Revenue Agency</td><td><p class="alignCenter">Exempt</p></td><td><p class="alignCenter">Exempt</p></td><td><p class="alignCenter">Exempt</p></td><td><p class="alignCenter">Exempt</p></td><td><p class="alignCenter">Exempt</p></td></tr><tr class="alignTop"><td>Canadian Food Inspection Agency</td><td><p class="alignRight">$5M</p></td><td><p class="alignCenter">n/a</p></td><td><p class="alignRight">$2M</p></td><td><p class="alignRight">$5M</p></td><td><p class="alignRight">$1M</p></td></tr><tr class="alignTop"><td>Canadian Heritage</td><td><p class="alignRight">$1M</p></td><td><p class="alignCenter">n/a</p></td><td><p class="alignRight">$2M</p></td><td><p class="alignRight">$5M</p></td><td><p class="alignRight">$1M</p></td></tr><tr class="alignTop"><td>Canadian International Development Agency</td><td><p class="alignRight">$1M</p></td><td><p class="alignCenter">n/a</p></td><td><p class="alignRight">$2M</p></td><td><p class="alignRight">$5M</p></td><td><p class="alignRight">$1M</p></td></tr><tr class="alignTop"><td>Canadian Security Intelligence Service</td><td><p class="alignRight">$1M</p></td><td><p class="alignCenter">n/a</p></td><td><p class="alignRight">$2M</p></td><td><p class="alignRight">$5M</p></td><td><p class="alignRight">$1M</p></td></tr><tr class="alignTop"><td>Canadian Space Agency</td><td><p class="alignRight">$5M</p></td><td><p class="alignCenter">n/a</p></td><td><p class="alignRight">$5M</p></td><td><p class="alignRight">$5M</p></td><td><p class="alignRight">$5M</p></td></tr><tr class="alignTop"><td>Citizenship and Immigration Canada</td><td><p class="alignRight">$1M</p></td><td><p class="alignCenter">n/a</p></td><td><p class="alignRight">$5M</p></td><td><p class="alignRight">$10M</p></td><td><p class="alignRight">$1M</p></td></tr><tr class="alignTop"><td>Correctional Service Canada<br />
      construction projects</td><td><p class="alignRight">$1M</p></td><td><p class="alignRight">$18M</p></td><td><p class="alignRight">$2M</p></td><td><p class="alignRight">$5M</p></td><td><p class="alignRight">$3M</p></td></tr><tr class="alignTop"><td>Department of Foreign Affairs and International Trade (see note)Staff Quarters and Miscellaneous<br />
      Chanceries - Lease<br />
      Chanceries - Construction<br />
      Official Residences</td><td><p class="alignRight">$1M</p></td><td><p class="alignRight">$30M<br />
        $15M<br />
        $3M</p></td><td><p class="alignRight">$2M</p></td><td><p class="alignRight">$5M</p></td><td><p class="alignRight">$1M</p></td></tr><tr class="alignTop"><td>Environment Canada</td><td><p class="alignRight">$2.5M</p></td><td><p class="alignCenter">n/a</p></td><td><p class="alignRight">$2M</p></td><td><p class="alignRight">$5M</p></td><td><p class="alignRight">$2.5M</p></td></tr><tr class="alignTop"><td>Fisheries and Oceans Canada</td><td><p class="alignRight">$20M</p></td><td><p class="alignCenter">n/a</p></td><td><p class="alignRight">$2M</p></td><td><p class="alignRight">$5M</p></td><td><p class="alignRight">$20M</p></td></tr><tr class="alignTop"><td>Health Canada<br />
      First Nations and Inuit Health Branch</td><td><p class="alignRight">$1M</p></td><td><p class="alignRight">$2M</p></td><td><p class="alignRight">$5M</p></td><td><p class="alignRight">$10M</p></td><td><p class="alignRight">$1M</p></td></tr><tr class="alignTop"><td>Human Resources Development Canada</td><td><p class="alignRight">$1M</p></td><td><p class="alignCenter">n/a</p></td><td><p class="alignRight">$5M</p></td><td><p class="alignRight">$10M</p></td><td><p class="alignRight">$1M</p></td></tr><tr class="alignTop"><td>Indian and Northern Affairs Canada</td><td><p class="alignRight">$15M</p></td><td><p class="alignCenter">n/a</p></td><td><p class="alignRight">$2M</p></td><td><p class="alignRight">$5M</p></td><td><p class="alignRight">$1M</p></td></tr><tr class="alignTop"><td>Industry Canada</td><td><p class="alignRight">$1M</p></td><td><p class="alignCenter">n/a</p></td><td><p class="alignRight">$2M</p></td><td><p class="alignRight">$5M</p></td><td><p class="alignRight">$1M</p></td></tr><tr class="alignTop"><td>National Defence<br />
      construction projects</td><td><p class="alignRight">$1M</p></td><td><p class="alignRight">$60M</p></td><td><p class="alignRight">$30M</p></td><td><p class="alignRight">$30M</p></td><td><p class="alignRight">$30M</p></td></tr><tr class="alignTop"><td>National Library of Canada</td><td><p class="alignRight">$1M</p></td><td><p class="alignCenter">n/a</p></td><td><p class="alignRight">$2M</p></td><td><p class="alignRight">$5M</p></td><td><p class="alignRight">$1M</p></td></tr><tr class="alignTop"><td>National Research Council Canada</td><td><p class="alignRight">$5M</p></td><td><p class="alignCenter">n/a</p></td><td><p class="alignRight">$2M</p></td><td><p class="alignRight">$5M</p></td><td><p class="alignRight">$5M</p></td></tr><tr class="alignTop"><td>Natural Resources Canada</td><td><p class="alignRight">$5M</p></td><td><p class="alignCenter">n/a</p></td><td><p class="alignRight">$5M</p></td><td><p class="alignRight">$10M</p></td><td><p class="alignRight">$5M</p></td></tr><tr class="alignTop"><td>Parks Canada<br />
      New National Parks, National Marine<br />
      Conservation Areas, National Historic Sites</td><td><p class="alignRight">$10M</p></td><td><p class="alignRight">$15M</p></td><td><p class="alignRight">$1M</p></td><td><p class="alignRight">$3M</p></td><td><p class="alignRight">$1M</p></td></tr><tr class="alignTop"><td>Public Works and Government Services Canada<br />
      office space </td><td><p class="alignRight">$5M</p></td><td><p class="alignRight">$30M</p></td><td><p class="alignRight">$2M</p></td><td><p class="alignRight">$5M</p></td><td><p class="alignRight">$1M</p></td></tr><tr class="alignTop"><td>Royal Canadian Mounted Police<br />
      detachments and subdivisions</td><td><p class="alignRight">$3M</p></td><td><p class="alignRight">$5M</p></td><td><p class="alignRight">$5M</p></td><td><p class="alignRight">$10M</p></td><td><p class="alignRight">$3M</p></td></tr><tr class="alignTop"><td>Statistics Canada</td><td><p class="alignRight">$1M</p></td><td><p class="alignCenter">n/a</p></td><td><p class="alignRight">$5M</p></td><td><p class="alignRight">$10M</p></td><td><p class="alignRight">$1M</p></td></tr><tr class="alignTop"><td>Transport Canada</td><td><p class="alignRight">$15M</p></td><td><p class="alignCenter">n/a</p></td><td><p class="alignRight">$15M</p></td><td><p class="alignRight">$15M</p></td><td><p class="alignRight">$15M</p></td></tr><tr class="alignTop"><td>Veterans Affairs Canada</td><td><p class="alignRight">$1M</p></td><td><p class="alignCenter">n/a</p></td><td><p class="alignRight">$2M</p></td><td><p class="alignRight">$5M</p></td><td><p class="alignRight">$1M</p></td></tr><tr class="alignTop"><td>All other departments and agencies</td><td><p class="alignRight">$1M</p></td><td><p class="alignCenter">n/a</p></td><td><p class="alignRight">$1M</p></td><td><p class="alignRight">$3M</p></td><td><p class="alignRight">$1M</p></td></tr></table><p><strong>Notes:</strong></p><ol><li>Department of Foreign Affairs and International Trade
  <ol class="lower-alpha"><li>Authorities apply to projects outside Canada.</li><li>For chanceries and official residences, levels apply to PPA; Treasury Board authority for EPA is not required if 
    the substantive estimate does not exceed the indicative estimate on which PPA was based.</li></ol></li><li>Government On-Line: special limited time flexibilities apply to certain participating departments.</li><li>For Preliminary and Effective Project Approval, dollar limits apply to total cost in current 
or budget-year dollars. </li><li>For Lease Project Authorities, the present value cost applies. The levels 
include both GST and HST.</li></ol></appendix><appendix anchor="F" title="Appendix F - Project Brief"><p>1. A project brief must accompany all submissions for Major Crown projects. While a project brief is not always required 
for other projects, it may be useful for submissions of complex and significant projects. It provides a summary of the full 
scope of the project, permitting the PPA and EPA documents to be written as succinctly as possible.</p><p>2. The project brief includes descriptions of:</p><p>2.1 the relationship of the project to the sponsoring department's mandate and programs and to government-wide objectives;</p><p>2.2 the scope, cost and other critical objectives that form the project baseline;</p><p>2.3 the level of service or capability to be developed or improved and a general description of the end product;</p><p>2.4 the results of benefit-cost and option analyses and a description of each option considered. Comparison of 
options should be based on at least a preliminary asset life-cycle cost estimate for each. Any strategic direction that 
has been given approval-in-principle or that limits available options should be provided;</p><p>2.5 the management approach to the overall project including the following:</p><p>2.5.1 the phasing of major work and the approach proposed for managing the project throughout its life;</p><p>2.5.2 the proposed timing of reports to the Treasury Board (in the case of Major Crown projects) and future submissions, 
when required;</p><p>2.5.3 the roles of participating departments and of the different units within the department,</p><p>2.5.4 the nature and extent of consultation with the Treasury Board Secretariat and other central agencies;</p><p>2.5.5 other features of the project that could affect its progress; and,</p><p>2.5.6 the options for terminating federal involvement.</p><p>2.6 The estimated schedule from the start of project definition to completion of the project. The schedule has 
appropriate allowances for the time required between the end of project definition and the start of project implementation. 
It also includes the proposed strategy for soliciting and awarding relevant contracts; and,</p><p>2.7 Agreements involving: international cooperation, federal-provincial relations or other government programs, 
joint federal-provincial undertakings, environmental assessments, reduction of regional disparities, or other national objectives 
applicable to the project. The description must distinguish between existing agreements that affect the project and agreements 
entered into specifically to further the project, or required before progress can be made. Drafts of agreements and similar 
documents should accompany the project brief.</p><p>3. Information requirements as identified under "Supporting Documentation" in Appendices A, B and C must also be included 
in the brief.</p></appendix><appendix anchor="G" title="Appendix G - Use of Estimates in Treasury Board Submissions"><p>1. This appendix is intended to clarify the use of cost estimates in PPA, EPA and LPA submissions.</p><p>2. Cost estimates must have a sufficiently high degree of quality and reliability to support Treasury Board's consideration 
of the project or specific phase of the project. In general, this will be a substantive cost estimate as defined below. 
Project approval, at either the definition or implementation phase, will include a cost ceiling (or cost objective) for 
the specified deliverables and timeframe. This establishes the baseline objectives against which the project team and departmental 
management can reasonably be held accountable.</p><p>3. For greater clarity, previous classes of estimates (A, B, C, and D) have been replaced by two types of estimates,
<em>substantive</em> and <em>indicative</em> estimates.</p><p>4. A substantive estimate is one of high quality and reliability and is based on:</p><p>4.1 detailed system and component design, design adaptation, workplans and drawings for components, construction or assembly, 
and installation. It includes site acquisition, preparation and any special requirements estimates. Contingency funding 
requirements must be justified based on line-by-line risk assessments, including market factors, industrial capability and 
labour considerations;</p><p>4.2 all significant and identifiable deliverables, as well as the costs of the government's contribution to employee 
benefit plans (20 percent of all salaries charged to the project);</p><p>4.3 all agreed objectives, including those resulting from procurement review; and,</p><p>4.4 market assessment, where acquisition is through lease, lease purchase or capital lease. The provisional allowance 
for fit-up or special tailoring requirements will be subject to review and possible revision at the contract approval stage.</p><p>5. When preparing the substantive estimate, the department must consult with appropriate common service organizations 
and its own operational and maintenance authorities.</p><p>6. In some cases, with the agreement of the department, the Treasury Board will use the substantive estimate as a form 
of a cap or design-to-cost figure.</p><p>7. An indicative estimate is an order-of-magnitude estimate that is not sufficiently reliable to warrant Treasury Board 
approval as a cost objective. It provides a rough cost projection used for budget planning purposes in the early stages 
of concept development of a project. It is usually based: on an operational statement of requirement (SOR), a market assessment 
of products and technological availability that would meet the requirement and other considerations such as implementation, 
life cycle costs and operational savings. The estimate will improve as the department:</p><p>7.1 invests in further concept development and prepares the SOR in greater detail;</p><p>7.2 identifies levels of risk and the corresponding costs to reduce them;</p><p>7.3 carries out a preliminary analysis of sources of supply;</p><p>7.4 assesses technological and production readiness; and,</p><p>7.5 identifies and refines the activities within the project definition and implementation phases.</p><p>8.When developing the estimates, the department must consult with appropriate common service organizations.</p></appendix></appendices></doc>