ARCHIVED - Estimate Project Resource / Schedule Basic Procedure

Warning This page has been archived.

Archived Content

Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.



An Enhanced Framework for the Management of Information Technology Projects

PPTO-PD-002 Estimate Project Resources/Schedule Basic Procedure

January 2000
Chief Information Officer Branch
Treasury Board of Canada Secretariat



1. Introduction

1.1  Purpose

This procedure is an activity in the Project Planning Process (PPTO-PS-002). It uses the output of the Estimate Software Product Size Basic Procedure to calculate effort, schedule and costs.

1.2 Scope

This document is applicable to any Information Management/Information Technology (IM/IT) project that is delivering software.

Ensure that all assumptions, constraints and rationale (i.e. decisions) are documented in the Project Plan.

1.3 Roles

Everyone in the organisation has a role to perform in this procedure.

Role Description/Responsibilities
Project Leader (PL) This is the person appointed by the sponsoring department to be accountable for all external and internal aspects of a capital project. http://www.tbs-sct.gc.ca /pubs_pol/dcgpubs/TBM_122/abkglos-eng.asp
Project Manager (PM) This is a person formally appointed to manage a project with specific accountability for achieving defined project objectives within allocated resources. A project manager has access to, and a formally defined relationship with, the project leader to which the specific project has been assigned. http://www.tbs-sct.gc.ca /pubs_pol/dcgpubs/TBM_122/abkglos-eng.asp
Project Team Member (PTM) Software engineer or writer assigned to a project

Responsible for completing project tasks, providing input to plans, and providing status

Project Management Office (PMO) This is a distinct and temporary organisational unit led by the project manager tasked to administer a project. It consists of assigned full or part-time members of the sponsoring department and, when appropriate, representatives of participating departments working together in accordance with any interdepartmental agreements or memorandums of understanding. 
Quality Assurance (QA ) Responsible for support of quality assurance activities.
Configuration Management (CM) Responsible for support of configuration management activities.

1.4 Definitions and Acronyms

Refer to Enhanced Management Framework Lexicon.

Refer to Enhanced Management Framework Acronyms.

Refer to Enhanced Management Framework Web Links.

1.5 References

1.5.1 Traceability

This procedure was designed to satisfy the SEI Software Capability maturity goals for Level 2 Key Practice: Software Project Planning.

1.5.2 Policies

Treasury Board Secretariat Policies:

  • Capital Plans - Glossary
  • Management of Major Crown Projects
  • Procurement Review Policy
  • Project Management
  • Project Approval

The policies above are located at the following URL:

http://www.tbs-sct.gc.ca /pubs_pol/dcgpubs/TBM_122/siglist-eng.asp

1.5.3 Standards

Annex A – Flowcharting Symbols

1.5.4  Processes

PPTO-PS-002 Project Planning Process

PPTO-PS-003 Project Tracking and Oversight Process

PEER-PS-001 Peer Review Process

1.5.5 Procedures

PPTO-PD-001 Estimate Software Product Size Basic Procedure

1.5.6 Guidelines

Not applicable at this time.

1.5.7 Templates

PPTO-TM-001 Process/Procedure Template

PPTO-TM-002 Project Plan Template

PPTO-TM-003 Project Estimates Template

1.5.8 Checklists

PPTO-CK-001 Project Management Checklist



2. Procedure

2.1 Entry Criteria

The following entry criteria describe the input's state, an event, or an expired amount of time, which is required before this procedure can begin.

Details of Entry Criteria
  • Approved Business Case
  • Approved Project Charter
  • Approved Set of Requirements
  • Initial Project Plan

2.2 Procedure Map

The overall procedure flow given below shows the interaction and flow among the activities. More details about the activity steps can be found in 2.4 Activities.

Estimate Project Resource/Schedule (13514 bytes)

2.3 Inputs

The following inputs are used in this procedure. Where they don't exist, identify any associated risks.

Input Detail of Inputs and Remarks Ref.
Business Case The identification and justification of an IM/IT project that relates the IM/IT project to program priorities and the measurable improvements in program performance.

- Identifies the opportunity

- Describes the added value

- Describes the IM/IT solution

- Identifies the indicators to measure improvements in program performance
EMF Business Case Guideline
Project Charter An agreement between technical and business groups defining:

- Partners & external stakeholders

- Project management framework

- Roles, responsibilities, accountabilities and activities

- Management commitments

- Empowerment framework
EMF Project Charter Template
Initial Project Plan Living agreement between the technical and business groups describing in greater detail the:

- What: interim and final deliverables

- Why: purpose and objectives

- Where: scope Who: roles, responsibilities, accountabilities

- How: managerial and technical processes, supporting plans

- When: schedule estimates

- How much: resource estimates

Document what detail is known.
PPTO-TM-002
  - The above document decisions made to date that will affect the risks, constraints, assumptions and estimates.  
Requirements - Requirements should be documented in accordance with the methodologies used.  
Software Size - Need the Total KSLOC calculated at the end of the Estimate Software Product Size – Basic Procedure PPTO-TM-002

PPTO-TM-003

Enterprise Database - Actuals from previous IM/IT projects for comparison and verification of the planning process  

2.4 Activities

The following activities are performed in this procedure. Document all assumptions, risks, constraints, etc. in the Project Plan.

No. Activities Action by Detail of Activities and Remarks Ref.
1 Determine Effort PM - Decide if New Development (top half of table) or Maintenance (bottom half of table)

- Determine Type Of Application (1A) Determine Size Domain (1B) using the Total KSLOC input from the Estimate Software Product Size Procedure

- Select and enter the Productivity Value (1D) where the Type of Application intersects with the Size Domain

- Effort in Person Months (1E) is automatically calculated by dividing the Total KSLOC by the Productivity Value (1D) and multiplying by 12 (months)

Note: As the Productivity Value increases, the effort decreases. (i.e., a military system will require more effort than an IT in house system)
PPTO- TM-002

PPTO- TM-003

2 Calculate Optimum Schedule (Duration) PM - Select and enter the Schedule Multiplier (2A) from the table column (1C)

- The Optimum Schedule (2B) is then automatically calculated by taking the sub root of the Effort in Person Months (1E) and multiplying by 2.6. This equation is derived from a statistical analysis of hundreds of projects done for the Constructive Cost Model (COCOMO) 11

- Is there an Imposed Schedule (from the Project Charter or Business Case)?

[YES] Go to Activity 3

[NO] Go to Activity 5

Note: The Schedule Multiplier and the formula used to calculate the Optimum Schedule are based on statistical analysis found in the References Section.

Note: The Optimum Schedule is the Duration in Calendar Months. It is also the schedule required to produce the lowest cost. Decreasing or increasing the duration increases cost.
PPTO- TM-002

PPTO- TM-003

3 Verify Imposed Schedule PM - The Schedule Acceleration (3B) is automatically calculated by dividing the Imposed Schedule (from the Project Charter or Business Case) by the Optimum Schedule (2B)

Note: Statistics verify that if the Schedule Acceleration is less than 0.75, then the schedule is impossible to meet!

Note: If the duration in Activity 2 is not acceptable, then effort must be added to the project.
PPTO- TM-002

PPTO- TM-003

4 Adjust Effort to Meet Imposed Schedule PM - Enter the Schedule Adjustment (4B) from the table column (4A)

- The Adjusted Total Effort in Person Months (4C) is automatically calculated by multiplying the Effort in Person Months (1E) by (4B)
PPTO- TM-002

PPTO- TM-003

5 Calculate Labour Costs Project Manager - Enter the Average Developer Cost Per Person Month (5A) in Thousands of Dollars (K$/PM)

- The Total Labour Costs for Optimum Schedule (5B) is automatically calculated by multiplying Effort in Persons Months (1E) by (5A)

- The Total Labour Costs for Imposed Schedule (5C) is automatically calculated by multiplying Adjusted Effort in Person Months (4C) by (5A)

Note: The Average Developer Cost Per Person Month should be based on input from your own organization.

PPTO- TM-002

PPTO- TM-003
6 Calculate Capital Costs Project Manager - Enter any other costs associated with the project into the spreadsheet using headings and items meaningful to your particular organization. The Total Capital Costs (6Z) are totalled

- A summary is provided for comparison
PPTO- TM-002

PPTO- TM-003

2.5 Outputs

The following outputs are produced or modified by the activities in this procedure.

Output Detail of Outputs and Remarks Ref.
Resources/Schedule Estimates - Project Schedule

- Project Effort

- Total Project Costs

- Background Information (Assumptions)

- Use the spreadsheet to calculate the resource/schedule estimates

- Append the spreadsheet to the project plan

- Document all assumptions, risks, constraints, etc. in the project plan
PPTO-TM-002

PPTO-TM-003

2.6 Verification and Validation

Output Validation To determine if the outputs are within specification,

- Use the (PEER-PS-001) Peer Review Process and any techniques described in your IM/IT methodology.

- Use validation techniques referred to in your IM\IT methodology such as testing, demonstration, analysis and inspection.

2.7 Exit Criteria

Details of Exit Criteria
  • All affected groups and individuals agree upon the resources/schedule estimates and sign-off

2.8 Metrics

Refer to Enhanced Management Framework, Exposure Draft Executive Toolkit, November 22, 1999 for the Project Health Check Dashboard.

2.9 Records Control Table

Not applicable at this time. Populate table if seeking ISO certification. For more information, refer to (PPTO-TM-001) Process/Procedure Template.

Description
(no. and name)
Storage Location Filing / Index Minimum Storage Period
       
       
       
       

2.10 Controlled Documents Table

Not applicable at this time. Populate if seeking ISO certification. For more information, refer to (PPTO-TM-001) Process/Procedure Template.

Number Name Revision Date
(or version)
Owner
       
       


Annex A – Lexicon

Refer to the Enhanced Management Framework Lexicon or insert a reference to your organisation's Lexicon.

Annex B – Acronyms

Refer to the Enhanced Management Framework Acronyms or insert a reference to your organisation's Acronyms.

Annex C – Flowcharting Symbols

Flowcharting Symbols
Parallelograms represent inputs and outputs to or from a process/procedure.
Flowcharting Symbols Flowcharting Symbols
Rectangles represent individual process/procedure activities. Diamonds represent important decision points in the process/procedure.
Flowcharting Symbols

Flowcharting Symbols
Flowcharting Symbols
Lines with arrowheads connect symbols to show the progression or direction of the activities. Circles represent connectors when a process/procedure flowchart continues on the next page.

Annex D – Bibliography

Boehm, Barry, Software Engineering Economics, Prentice Hall, New Jersey, 1991.

Jones, Capers, Applied Software Measurement: Assuring Productivity and Quality, McGraw-Hill, Inc., New York, 1996.

Refer to Enhanced Management Framework Web Links.

Annex E – Document Change Control

This chart contains a history of this documents revision. The document itself should be stored in revision control, and a brief description of each version should be entered in the revision control system. That brief description can be repeated in this section.

Revision Number Date of Issue Author(s) Brief Description of Change
0.1 1999-09-08 R. Mundt Initial Document
0.2 1999-09-22 R. Mundt Revised Draft
0.3 1999-09-23 R. Mundt Added Spreadsheet Annex
1.0 1999-11-09 EMF/PPTO First Draft
2.0 2000-01-21 EMF/PPTO Second Draft

Annex F – Project Estimates Formula(s) Documentation for Project Resources and Schedule – Sheet 2

Size (Bring forward Total KSLOC from previous sheet)
(Sheet 1 - 5C) Total KSLOC  
1. Effort
Productivity Value (1C) Schedule Multiplier
(1A) Type of Application (1B) Size Domain
Small

0–60 KSLOC
Medium

61-250 KSLOC
Large

> 250 KSLOC
New Development        
IT Outsourcing 4.5 4.0 3.0 1.12
IT In House 3.0 3.6 2.7 1.12
Commercial Software / Simulators 2.0 2.5 2.0 1.20
Embedded Systems 1.6 1.5 1.0 1.32
Military Standard Embedded Systems 2.0 1.2 0.8 1.32
Ada Military Standard Embedded 2.0 2.2 2.5 1.32
Embedded Object Oriented 2.2 2.4 2.6 1.32
Maintenance        
IT Outsourcing 3.2 2.8 2.1 1.12
IT In House 2.1 2.5 1.9 1.12
Commercial Software / Simulators 1.4 1.8 1.4 1.20
Embedded Systems 1.1 1.1 0.7 1.32
Military Standard Embedded Systems 1.4 0.8 0.6 1.32
Ada Military Standard Embedded 1.5 1.5 1.8 1.32
Embedded Object Oriented 1.5 1.7 1.8 1.32
(1D) Productivity Value Intersection of "Type of Application" & "Size Domain"
(1E) Effort in Person Months (Sheet 1 – 5C) / (1D) * 12
2. Optimum Schedule
(2A) Schedule Multiplier Choose from Column 1C
(2B) Optimum Schedule (Duration in Calendar Months) (2.6 * (Cube root of 1E)) * 2A
If no imposed schedule go to step 5 Labour Costs.
3. Imposed Schedule
(3A) Imposed Schedule (Duration in Calendar Months) From Business Case or Project Charter
(3B) Schedule Acceleration 3A / 2B
4. Effort Adjustment to Meet Imposed Schedule
Description (4A) Adjustment
Schedule Acceleration < 0.75 None

Schedule is Impossible
Schedule Acceleration 0.75 – 0.80 1.23
Schedule Acceleration 0.81 – 0.95 1.08
Schedule Acceleration > 0.95 1.0
(4B) Schedule Adjustment Choose from Column 4A
(4C) Adjusted Total Effort in Person Months (1E) *(4B)
5 Labour Costs
(5A) Average Developer Cost Per Person Month Use Organization's Average
(5B) Total Labour Costs for Optimum Schedule 1E * 5A
(5C) Total Labour Costs for Imposed Schedule 4C * 5A
6 Capital Costs
(6A) Development/Maintenance Environment    
Hardware    
Software    
Other    
(6B) Infrastructure Costs    
Server/Network Systems    
Telecom Access    
Other    
(6C) Additional Costs    
Training    
Accommodations    
Translation    
Other    
     
(6Z) Total Capital Costs   Sum column
7 Summary
Size (Sheet 1 – 5C)
  (1E)
Optimum Schedule (Duration in Calendar Months) (2B)
Total Labour Costs for Optimum Schedule (5B)
Imposed Schedule (Duration in Calendar Months) (3A)
Adjusted Total Effort in Person Months (To Meet Imposed Schedule) (4C)
Total Labour Costs for Imposed Schedule (5C)
Total Capital Costs (6Z)